The Hitachi Verification Train
In 2002, the promise of potential rolling stock orders in UK lead the Japanese manufacturer Hitachi to investigate the possibility of entering the market. Recent experience of others in respect of excessive time taken in acquiring a Safety Case to allow the trains to enter service in the UK suggested to Hitachi that it would be worthwhile investing money in a test train to evaluate their traction in the UK environment. This would avoid expensive delays in the future. This resulted in a contract being let to AEA Technology Rail at Derby to convert a Class 310 EMU into a test train capable of running on both AC and DC supplies. An original 25kV power car was fitted with the Hitachi traction package, including transformer and traction motors. The train could operate on either 25kV AC via the original pantograph on the converted power car or from 3rd rail 650 v DC fed to the power car via cables through the train from shoe gear fitted underneath the cabs of the 310 unit. The tests needed to be carried out initially at specific sites which were to be electrically isolated from the rest of the railway and therefore the train needed conventional traction in order to transit from the depot to the test site prior to switching in the Hitachi traction. To this end the AC version of the train was made up of an original 310 AC power car, two driving trailers and the converted Hitachi power car. In addition for DC operation a class 423 DC power car was acquired which replaced the 310 power car. The train was known as the 'Verification Train' or V-Train was numbered 960201 and the author was involved with the on-track testing of the train during which time it undertook test running on both DC and AC lines as well as on the CTRL itself. The fact that Hitachi eventually won the order for the domestic CTRL services appears to have justified the decision to verify that the traction did not interfere with the infrastructure. |
Here is a selection of photos of the V-train
Click on the picture for a bigger image - all photos are the author's unless otherwise credited
DC testing
This was undertaken on the line between Faversham and Margate, the train being based at Ramsgate depot. The tests were carried out in two stages, first within a Signal Protection Zone (SPZ) which was put in place overnight on the Down line between Margate and Whitstable and following satisfactory results the train ran in off-peak traffic between Ramsgate and Faversham. |
AC testing
This was undertaken on the line between Shenfield, Southminster and Southend, the train being based at Ilford depot. The tests were carried out in two stages, first within a Signal Protection Zone (SPZ) which was put in place overnight on both Up and Down lines between either Shenfield and Southminster or between Shenfield and Southend. Following satisfactory results the train ran in off-peak traffic between Shenfield and Southend. |
CTRL testing
This was undertaken over a couple of nights towards the
end of March 2005 running between Singlewell and Sandling Tunnel. Total possession of the CTRL was necessary although the train ran up and down the Up line only, based at the Up freight loop at Lenham. |
Following the completion of the test series at the end of March 2005 the unit languished on Ilford depot until the end of May when it was hauled off to the MOD scrapping site at Shoeburyness where it was finally scrapped. |